Ultimate Turbocharger Installation Guide: Step-by-step for Garrett Gt35 Series on 2jz Engines

Installing a turbocharger can significantly enhance the performance of your 2JZ engine. The Garrett GT35 series is a popular choice among enthusiasts for its reliability and power capabilities. This guide provides a comprehensive step-by-step approach to installing a Garrett GT35 turbocharger on a 2JZ engine.

Tools and Materials Needed

  • Garrett GT35 Turbocharger
  • Turbo manifold
  • Downpipe
  • Oil feed and return lines
  • Intercooler and piping
  • Silicone couplers
  • Gaskets
  • Wrenches and sockets
  • Torque wrench
  • Thread sealant

Preparation

Before beginning the installation, ensure that you have all necessary tools and materials at hand. Begin by disconnecting the battery and draining the engine oil to prevent any spills during the installation process.

Removing the Old Turbocharger

If you are replacing an existing turbocharger, follow these steps to remove it:

  • Disconnect the oil feed and return lines.
  • Remove the downpipe and any associated hardware.
  • Unbolt the turbo from the manifold.
  • Carefully lift the old turbocharger out of the engine bay.

Installing the Garrett GT35 Turbocharger

With the old turbo removed, you can now proceed to install the new Garrett GT35 turbocharger. Follow these steps:

  • Place the new turbocharger onto the turbo manifold.
  • Secure the turbo with the appropriate bolts, ensuring they are tightened to the manufacturer’s specifications.
  • Install new gaskets to prevent leaks.
  • Connect the oil feed and return lines, using thread sealant where necessary.
  • Install the downpipe, ensuring it aligns correctly with the exhaust system.

Intercooler and Piping Setup

After securing the turbocharger, you will need to set up the intercooler and piping:

  • Install the intercooler in a suitable location, ensuring it has adequate airflow.
  • Connect the piping from the turbocharger to the intercooler.
  • Use silicone couplers to ensure flexible connections that can withstand boost pressure.

Finalizing the Installation

Once the turbocharger and intercooler are installed, complete the installation by following these final steps:

  • Reconnect the battery.
  • Fill the engine with fresh oil, ensuring the correct level is maintained.
  • Check all connections for tightness and leaks.

Testing the Installation

Before taking your vehicle for a drive, it is crucial to test the installation:

  • Start the engine and let it idle for a few minutes.
  • Check for any oil leaks or exhaust leaks.
  • Monitor oil pressure and temperatures to ensure everything is functioning correctly.

Conclusion

Installing a Garrett GT35 turbocharger on a 2JZ engine can greatly improve performance and driving experience. By following this guide, you can ensure a successful installation. Remember to always consult the manufacturer’s instructions and specifications for the best results.